Provision of land use and development assessment services to applicants and the community including advice and determination of applications

Time taken to decide planning applications

Median number of days taken between receipt of a planning application and a decision on the application

Surf Coast Shire (2019-2020)

76 days

Similar Councils (2019-2020)

61.66 days

All Councils (2019-2020)

65.41 days

Performance Trend

Reporting Period Surf Coast Shire Similar Councils All Councils
2016-2017 48 days 59.88 days 72.54 days
2017-2018 48 days 56.79 days 69.69 days
2018-2019 63 days 62.24 days 69.6 days
2019-2020 76 days 61.66 days 65.41 days

Surf Coast Shire Council Says...

There were a number of large complex applications in the year that took longer to process and pushed out the median number of days taken to decide planning permits.

Planning applications decided within required time frames

Percentage of VicSmart planning application decisions made within 10 days and regular planning application decisions made within 60 days

Surf Coast Shire (2019-2020)

80.88%

Similar Councils (2019-2020)

77.58%

All Councils (2019-2020)

73.97%

Performance Trend

Reporting Period Surf Coast Shire Similar Councils All Councils
2016-2017 71.02% 76.73% 70.06%
2017-2018 78.73% 75.63% 69.63%
2018-2019 83.93% 77.78% 70.17%
2019-2020 80.88% 77.58% 73.97%

Surf Coast Shire Council Says...

The improvement in service performance is due to IT system improvements, allocation of resources and training provided over a 5 year period as part of a Planning Customer Service Program.

Cost of statutory planning service per planning application

Direct cost to council of the statutory planning service per planning application received

Surf Coast Shire (2019-2020)

$2,716.98

Similar Councils (2019-2020)

$2,253.70

All Councils (2019-2020)

$2,645.65

Performance Trend

Reporting Period Surf Coast Shire Similar Councils All Councils
2016-2017 $1,141.63 $2,211.57 $2,311.71
2017-2018 $1,480.98 $2,097.80 $2,459.07
2018-2019 $2,909.65 $2,255.93 $2,615.43
2019-2020 $2,716.98 $2,253.70 $2,645.65

Surf Coast Shire Council Says...

The decrease is driven by a reduction in overall expenses in the Statutory Planning department of $40k, mainly attributed to a $30k reduction in legal fees. Total planning permit applications increased from 532 to 573.

Council planning decisions upheld at VCAT

Percentage of council planning application decisions subject to review by VCAT that were not set aside

Surf Coast Shire (2019-2020)

80.00%

Similar Councils (2019-2020)

60.43%

All Councils (2019-2020)

50.61%

Performance Trend

Reporting Period Surf Coast Shire Similar Councils All Councils
2016-2017 80.95% 66.30% 58.73%
2017-2018 50.00% 65.41% 61.19%
2018-2019 46.15% 49.83% 52.64%
2019-2020 80.00% 60.43% 50.61%

Surf Coast Shire Council Says...

During 2019-20 Council received a total of 573 planning applications. Of these 10 matters were referred to VCAT for review. This is the lowest number over the last four years, however the impact of COVID restrictions saw a number of matters deferred by VCAT until after the reporting period. Due to the variable nature of matters it is difficult to use percentages reported as a reflection of Council's performance.